Manual

Menu Process > Generate Quality Report - PIX4Dmapper

This article explains how to generate a quality report when using PIX4Dmapper.

Access: On the Menu bar, click Process > Generate Quality Report (enabled once step 1. Initial Processing has been completed).

PIX4Dmapper generate quality report

This process generates a new Quality Report that refers to the new reconstruction obtained after applying changes to the project once step 1. Initial Processing has been completed. Such changes can be:

  • Adding GCPs.
  • Adding Manual Tie Points.
  • Adding Check Points.
  • Changing coordinate systems.
  • Enabling/disabling images.
  • Running the Rematch and Optimize option.
Important: When adding GCPs, Manual Tie Points, Check Points, changing coordinate systems, or enabling/disabling images, the Reoptimize option has to be applied before generating the new Quality Report.